I need to set a part-time time resource (let's call him Jim, working from 8 AM to 12 AM, 50%) in Project 2007. I was wondering which of the following mehods is best:
1) to set a new calendar (8-12 AM from Monday to Friday) and to assign it to Joe;
2) to set Joe availability to 50%
I thought the former is the best choice, but when I assigned Joe a 16-hour work activity, duration was set 2 days! (I expected 4 days)! Using the second method, duration was automatically set to 4 days !
So, what's wrong with the fist method ?