Results 1 to 6 of 6

Thread: Saving the baseline work without modifying schedule in project 2010

  1. #1
    Join Date
    Dec 2011
    Posts
    42

    Saving the baseline work without modifying schedule in project 2010

    Is it accomplishable to save work to Baseline Work preclude altering my Baseline Start/Finish date. I seriously doubt you determine to locate numerous companies with the intention of do what you suggest. There are on the other hand companies to facilitate utilize Project for the scheduling, containing resource loading, and then dump to facilitate data into an additional application for earned value and financial processing. Other than the baseline is not set until the plan is resource loaded. Is it able to save the baseline work without modifying schedule in project 2010.

  2. #2
    Join Date
    Aug 2011
    Posts
    406

    Re: Saving the baseline work without modifying schedule in project 2010

    The part you are having trouble through is how be able to you have encompassed a valid schedule to facilitate runs well if it has no resources loaded. The idea of runs well becomes an counterfeited concept. Unloaded schedules get no matter what completed, they be able to merely represent a concept. Apparently resource loading the critical element of improvisation is missing. Anybody be able to position together a pretty schedule to facilitate and demonstrates the whole thing.

  3. #3
    Join Date
    Aug 2011
    Posts
    315

    Re: Saving the baseline work without modifying schedule in project 2010

    On the other hand on an occasion that schedule is loaded commencing from side to side the resources, the real task of project management comes into play. Do not misconceive, I am a perfectionist additional than not a purist. I have encompassed and worked through several users who desired to utilize Project in extremely unconventional ways, additional than this is not one of them.

  4. #4
    Join Date
    Aug 2011
    Posts
    358

    Re: Saving the baseline work without modifying schedule in project 2010

    The most excellent approach is to utilize a dissimilar baseline field. Your composite baseline data determine to be in two separate baseline fields additional than its quick and might be the entire you necessitate. You might in addition try manually entering the desired values directly into the Baseline Work field. If with the intention of does not work, I had originated to facilitate manual entry sometimes is not recognized in baseline fields, I suppose a VBA approach would work.

  5. #5
    Join Date
    Aug 2011
    Posts
    367

    Re: Saving the baseline work without modifying schedule in project 2010

    You be able to bring up to date an individual task is work to the innovative previously saved baseline work field, without altering the baseline start and the completed fields. You might alter the task type to fixed duration, then you have to bring up to date the work field. ON an occasion you have completed that, you be able to save with the intention of task to the baseline you have already other than the question you desire to ask.

  6. #6
    Join Date
    Aug 2011
    Posts
    326

    Re: Saving the baseline work without modifying schedule in project 2010

    If the scenario is to facilitate the innovative the planned work previously saved in the baseline field has altered, then you might desire to bring up to date to facilitate field, then update the baseline. On the other hand, if you desire to update the baseline through actual work, then this is not the appropriate method. My case scenario is I have encompassed already have schedules established. At present, I had just acquire to the position that I desire to start planning work.

Similar Threads

  1. Need help to create Microsoft Project 2010 Schedule
    By Tur^turro in forum Microsoft Project
    Replies: 4
    Last Post: 19-04-2012, 01:11 PM
  2. Replies: 1
    Last Post: 27-10-2011, 05:45 PM
  3. Error when saving MS Project 2010 file
    By shoppingboy in forum Microsoft Project
    Replies: 5
    Last Post: 04-10-2011, 02:42 PM
  4. Replies: 3
    Last Post: 29-06-2011, 09:31 PM
  5. How to revise Baseline in Microsoft Project
    By prafullanayana in forum Microsoft Project
    Replies: 2
    Last Post: 25-03-2008, 05:33 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,711,654,451.84536 seconds with 17 queries