Hi there
I am stuck on a very basic question. I have a construction project with many different dependencies on resources.
As part of the schedule, each person has to undergo a lot of training - the time of which must be scheduled in the project. So we have something like
So before any resource is able to be scheduled in to work on a task - they must have completed this training (and its different for each task)
So 6 guys working on 20 mining sites.
To work on any mining site, they must have undergone a 10 day generic training package.
To work on a single site, they must have completed a range of 6 days courses for that particular site.
To complete a risk assessment on a mine, they must have blood tests plus the above training.
To complete the works, the risk assessment must have been done (by any staff) and the resource for the works must have completed the relevant training courses.
I am really not sure how I can do this - I can set all the tasks up but when I try to allocate only properly trained people to the correct tasks, I fall down. And of course the training has to be part of the schedule as the work on any tasks cant start until that happens.
Can anyone help on how i set up constraints on resource/specific task?
The training is 10 days for generic (all resources will do at different times).
The task training is around 6 days.
Lots of men work on the different tasks and I need to allocate the correct resources to the right tasks or book them on correct training.
This is simplistic, it gets very complicated with the number of different training/work allowed permutations
if anyone could help I would really appreciate it!