    Hi all,

    please can U advice how to set SS with a lag and FF simultanously in MS Project?

    I have 3 tasks: A, B, C

    Task B starts N days before A and ends the day C ends.

    Sample:
    Task A = development
    Task B = development environment preparation & support
    Task C = UAT (user acceptance tests)

    Task B needs to start with environment preparation at least 30 days before development will start (Task A SS-30d) and to finish together with UAT (Task C FF).

    I found an existing discussion ===> SS and FF simultaneously with a solution described here ===>
    http://support.microsoft.com/kb/141733 (Hammock task) but in addition to this I need to start the task N days earlier.

    Please does exist an elegant solution for this?

    Thank you, Dag.

  2. #2
    Join Date
    Dec 2006
    Posts
    489

    Re: SS, FF and a lag simultaneously

    Hello Dag,

    The Hammock tasks cannot have lead or lag but you could create milestones which have the start date of Task A. Then link B to the milestone with the lead.

    I hope this helps.

    Jlie

  3. #3
    Join Date
    Feb 2012
    Posts
    2

    Re: SS, FF and a lag simultaneously

    Hi Julie,

    thank you very much. I'm trying to avoid creating milestones for these tasks even I believe it would be the most transparent way.

    Other option I figured out is to create Task B with following Task information:

    end date = link to Task C End Date (UAT end date)
    predecessor = Task A SS - N days (N days before Development start date)

    Thank you and good luck, Dag.

Similar Threads

  1. SS and FF simultaneously
    By newtolivieri in forum Microsoft Project
    Replies: 8
    Last Post: 06-06-2011, 05:57 PM
  2. Cannot use VPC and VMware simultaneously!!!
    By Catawba in forum Operating Systems
    Replies: 5
    Last Post: 21-08-2010, 01:49 AM
  3. JDK and Eclipse installation simultaneously
    By Rivan in forum Software Development
    Replies: 4
    Last Post: 15-07-2010, 12:42 AM
  4. 4 Users 1 PC simultaneously
    By macfiden in forum Networking & Security
    Replies: 3
    Last Post: 11-09-2009, 01:08 PM
  5. help: Use two routers simultaneously!
    By Adik in forum Networking & Security
    Replies: 2
    Last Post: 25-11-2008, 03:28 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,282,420.94403 seconds with 17 queries