    Visual Report - Budget cost report without baseline cost

    I've a project valued at only whit fixed cost, placed directly in the "Costs" field, without allocation of resources.

    I saved the baseline plan and after I changed the fixed costs, and now I find the two columns, one with the "Baseline cost" (save that of the baseline plan) and the other with the new fixed costs.

    When I go to generate a visual report can not find the baseline costs in the Excel PivotTable, which are always 0.

    This happens to me with any type of graphical report.


    Someone can help me?

    Thanks!!!

  2. #2
    Join Date
    Feb 2012
    Posts
    3

    Re: Visual Report - Budget cost report without baseline cost

    The question is about MS project 2007.

  3. #3
    Join Date
    Dec 2006
    Posts
    489

    Re: Visual Report - Budget cost report without baseline cost

    Hello Clauz,

    I'm guessing you are trying to use the Baseline Cost report which is based upon the Assignment cube. Without resources assigned, you have no costs coming from assignments and the "Baseline Cost" you see in the report are baseline assignment costs.

    Most of the Visual Reports are based upon assignment data so without resources assigned, I'm afraid they won't work for you.

    I'm guessing you want timescaled cost data in Excel? The best I can suggest, short of exporting the data out through VBA, is to show the data you want in the Task Usage view (right side) and carefully copy/paste into Excel.

    I hope this helps.
    Julie

  4. #4
    Join Date
    Feb 2012
    Posts
    3

    Re: Visual Report - Budget cost report without baseline cost

    Yes, you guessed everything.
    I'm going to copy the Task Usage!

    Thank you for your help!

  5. #5
    Join Date
    Dec 2006
    Posts
    489

    Re: Visual Report - Budget cost report without baseline cost

    Glad to have helped and thanks for the feedback.

    Julie

Similar Threads

  1. Report on resource cost
    By jamespaul.tg in forum Microsoft Project
    Replies: 1
    Last Post: 03-12-2011, 05:37 PM
  2. Cash Flow Report Total Cost Does Not Match Gantt Total Cost?
    By kaorisdad in forum Microsoft Project
    Replies: 5
    Last Post: 26-08-2011, 06:50 AM
  3. Replies: 5
    Last Post: 24-08-2011, 03:41 AM
  4. Replies: 3
    Last Post: 29-06-2011, 09:31 PM
  5. How to draw a graph of the cost baseline?
    By hindustnidude in forum Microsoft Project
    Replies: 3
    Last Post: 27-05-2008, 01:07 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,711,644,282.52535 seconds with 17 queries