Hello MVPs,
A challenging problem, for me atleast.
To put it in simple terms:-
--- 10 tasks all linked to FS, 5 day duration, 1 resource, Standard calendar & Base calendar (THG_Cal-7 in file) of M-F 5d x 8hrs
--- All activities in Red critical path, so far so good, please see attached file.
--- Once I change the calendar of Act-5 in the middle to Cal-2 (20hr x 7d), the critical path breaks up!
My querries are:-
1. How does MSP calculates critical path, based on Project Calender, Elapsed time, Task calender?
2. Is it possible in MSp to allocate calenders to logical links like Primavera P6 or other scheduling software
3. Why MSP calculates Total slack as 6days for Act-5, which means based on Task calender not Project calender?
4. Lastly Whats the wayout to indicate correct critical path incase your programme has >1000 activities?
Your comments would be much appreciated.
Cheers!
Calenders.zip