    Autosplit and level?

    Hello,

    I have a task that could take many hours. Although I would like to split this into many hours each day. This seems simple enough although I am not finding an easy way to do this in MS Project 2010. Attempting to split by mouse is tedious. I have defined my resource and allocated the task to the resource. From there I attempted to level and distributed but it does not do what I expected and it just rescheduled it. I suppose I don't have enough tasks yet for MS project to think correctly? I do have "leveling can create split in work" checked in leveling options as well. I also thought I could switch to task usage and define time per day; it appears duration and work time are two different entities. Please help

    Thank you,
    Bryan

  2. #2
    Join Date
    Dec 2006
    Posts
    489

    Re: Autosplit and level?

    If you want to manually split, I suggest apply the Task Usage or Resource Usage view. You can then edit the hours on a daily or hourly basis as needed. Enter zeros in the Work for the assignment row to create the splits.

    I hope this helps.
    Julie

Similar Threads

  1. Replies: 9
    Last Post: 18-12-2011, 12:14 PM
  2. How many level we are having in NFS The Run?
    By Duggars in forum Video Games
    Replies: 3
    Last Post: 16-11-2011, 10:46 PM
  3. Replies: 5
    Last Post: 27-08-2011, 10:28 PM
  4. Replies: 5
    Last Post: 07-06-2011, 10:52 AM
  5. Replies: 6
    Last Post: 10-03-2011, 05:51 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,716,283,165.85046 seconds with 17 queries