Hi,
I am constantly having troubles with the following issue:
I use projects to plan tasks and estimate duration for tasks for the use of building machines in our factory.
I start the project off by working towards my finish date as our customers expect the product by a due date.
I then set my baseline.
I'm having problems when I run overdue, the finish date won't update.
When I run overdue, I try to change the duration of the said task that is taking more time than planned.
And I get an error because of the predecessors.
I want to find a way so that if a task is scheduled to take 3 days but due to problems it ends up taking 5 days, I want all future tasks that are linked to this and the finish date to be pushed forward by these extra 2 days.
I can send you a copy of an example projects file I already have if need be.
Can anyone help me?
Regards,
Chris