    Updating Task with MSP 2007

    For the last few years I have been working with Primavera. I'm am starting to work with MS Project again and I can't seem to remember how to update the project without splitting tasks that are in progress.

    For example: Using the Project Update under tools yields the following: Tasks to the left of the current date are 100% complete - No problem. Tasks to the right of the current date have not started and are 0% complete - No problem. Tasks that should've started and have not, get moved to the current date. - No problem. Tasks that started prior to the current date have started on time and are on schedule to finish on the originally planned date. They are X% complete. - The task splits and pushes the end date past it's due date. - PROBLEM. I realize that I can adjust the remaining duration, but how can I keep the task from splitting?

  2. #2
    Join Date
    Dec 2007
    Posts
    2,291

    Re: Updating Task with MSP 2007

    I think that you can copy a cell in MSP and then paste the content as a link into another cell (through paste special, paste link). Just copying a date into the destination cell won't work because that will normally just impose a constraint and not change the duration.

  3. #3
    Join Date
    Dec 2006
    Posts
    489

    Re: Updating Task with MSP 2007

    Quote Originally Posted by TXConstructionGuy View Post
    For the last few years I have been working with Primavera. I'm am starting to work with MS Project again and I can't seem to remember how to update the project without splitting tasks that are in progress.

    For example: Using the Project Update under tools yields the following: Tasks to the left of the current date are 100% complete - No problem. Tasks to the right of the current date have not started and are 0% complete - No problem. Tasks that should've started and have not, get moved to the current date. - No problem. Tasks that started prior to the current date have started on time and are on schedule to finish on the originally planned date. They are X% complete. - The task splits and pushes the end date past it's due date. - PROBLEM. I realize that I can adjust the remaining duration, but how can I keep the task from splitting?
    Try Tools > Options, Schedule tab and uncheck "Split in-progress tasks".

    I hope this helps.
    Julie

  4. #4
    Join Date
    Dec 2011
    Posts
    2

    Re: Updating Task with MSP 2007

    Thanks so much for your help, JulieS. That is exactly what I was looking for.

  5. #5
    Join Date
    Dec 2006
    Posts
    489

    Re: Updating Task with MSP 2007

    You're most welcome and thanks for the feedback.
    Julie

Similar Threads

  1. Brewery Task Lengths for Project 2007
    By MrMatlock in forum Windows Software
    Replies: 1
    Last Post: 21-05-2011, 05:57 AM
  2. Ms Project 2007 Task setup
    By Mr Karlsson in forum Windows Software
    Replies: 1
    Last Post: 30-04-2011, 01:45 AM
  3. setup task in project 2007, need help!!
    By pc_s in forum Windows Software
    Replies: 2
    Last Post: 11-02-2011, 02:21 AM
  4. Project Professional 2007 task duration
    By iShree in forum Microsoft Project
    Replies: 3
    Last Post: 04-08-2009, 06:24 PM
  5. Viewing task in Outlook 2007
    By wazzeledozzle in forum Windows Software
    Replies: 4
    Last Post: 06-11-2008, 03:03 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,711,615,727.00967 seconds with 17 queries