I have a Project where I have had the software schedule all dates for me. I created tasks with durations and predecessors only. For some reason, I have some early tasks that are starting on the same day despite the fact that one is a predecessor to another -- the 2nd task should start when the first one ends. These are tasks that are 100% completed. Is my only option now to specify a start date?