Now that we have figured out how to copy a network diagram and have multiple ones in the same project, I need to branch out to three sets of dates ...
So the customer knows that the dates from some people are possibly off by a bit (what estimates aren't?). He wants to track them (baseline and start/finish) but also some other dates to compare where the dates would be if the dates were different - without just inputting the new dates in the start/finish columns and see what happens.
So my supervisor thinks we can use start1 and finish1 for the alternate dates. We thought that duration1 would automatically show the duration, but no.
So now I need to know how to write the formula. I am not a programmer. I tried a couple things, but they didn't work. I am not very good at Excel, either, so I have little knowledge base on formulas.
Can anyone tell me how to make duration1 show the timespan between start1 and finish1? Will it use the default calendar I have on this project?
Thanks!