I have the following set up for two tasks in the attached file:
1. Constraint type is "As Soon as Possible"
2. No dependencies, predecessors, etc.
3. Task not started
4. Project start date 10/7/2010
With the above why does my task start date show 1/3/12 rather than 10/7/2010. See attached file.