I am using Project 2007.
I am trying to show information from a text field in the 'Resource Usage' view. However, I need to enter that text information in the 'Gantt Chart' view.
I've used the 'Text1' field to enter the text in the 'Gantt Chart' view, but that is of course impossible to show in the 'Resource Usage' view (since the former is a task view and the later is a resource view, meaning the 'Text1' fields are completely different and non-transferable between the 2).
I've tried using the VBA macro, but don't really know what they're talking about or how to access the 'assignment Text fields'.
Bottom line is that I need to see text info entered in a field on the 'Gantt Chart' show up in the 'Resource Usage'. Can anyone help with this?? Much thanks!!