Hello
I looking for a solution, whether within MS Project functions or the use of a macro to automatically update the finish column date, if the Baseline date for that column is changed to a date over the Finish date, but still allows you to change the Finish date if needed.
Within my plan I have a Duration, Start, Baseline Finish and Finish columns. What I need is, if the Baseline Finish date for a activity is changed to date after the Finish date, it automatically updates the Finish date to the same as Baseline Date, but still allows you to change the Finish Column date, to date after Baseline Finish date, if the Milestone slips, and a date before Baseline Finish date, if the Milestone has been achieved before Baseline.
Hope that make sense.
Any help would be highly appreciated.
Bookmarks