I'm having a hard time with a problem. I found considerably satisfactory workaround, but I would like to learn how to fix this... I believe it's simple.
Consider 3 activities: 1, 2 and 3.
For 2: 1 is the predecessor (a standard "Finish-to-Start")
I would like activity 3 to start with activity 1 *and* finish with activity 2
The first thing I tried was:
For 3: 1SS,2FF
Project doesn't complain when I do this, but when I pin the "2FF", the beginning of activity 3 shifts for date after the beginning of activity 1.
The duration of 3 is maintained, that's why the start shifts. I would like the duration of 3 to be a result of the duration of 1 and 2.
Is this possible? What settings could I have messed up to avoid such behavior?
Thanks in advance!
Bookmarks