    MS Project 2010 Set Reminder

    I have MS Project 2010 and i cannot activate the "Set Reminder" function found in the tracking menu. This used to work well in ver 2007.

    Can any one help!!!

    Many thanks
    Andrew

  2. #2
    Join Date
    Dec 2007
    Posts
    2,291

    Re: MS Project 2010 Set Reminder

    You have to add this feature to an existing toolbar, please perfom the following steps:

    1. Got to Tools/Customize/Toolbars
    2. Switch to tab Commands
    3. Select All Commands
    4. Scroll to ReminderSet
    5. Drop the toolbar button on a toolbar of your choice
    6. Click Close

    This way now you can add a reminder in your local Outlook as task with reminder for selected Project tasks from you local MS Project.

  3. #3
    Join Date
    Jan 2011
    Posts
    2

    Re: MS Project 2010 Set Reminder

    I can see the function button, it is not highlighted so i am not able to use it.

  4. #4
    Join Date
    Dec 2006
    Posts
    489

    Re: MS Project 2010 Set Reminder

    What version of Outlook do you have installed? I don't see any problems using Project 2010 and Outlook 2010. I cannot reproduce what you report. Is this a clean installation of Project 2010 or do you have other previous versions of Project installed?

  5. #5
    Join Date
    Jan 2011
    Posts
    1

    Re: MS Project 2010 Set Reminder

    Hello,

    I have the same problem, the button "set reminder" is not highlighted. I use MS project 2010 and outlook 2007.

    Do you know where com from the problem?
    Thanks.

  6. #6
    Join Date
    Dec 2006
    Posts
    489

    Re: MS Project 2010 Set Reminder

    My *guess* is that you need the same version of Outlook as Project in order for the Set Reminders button to work.

Similar Threads

  1. Replies: 4
    Last Post: 20-04-2012, 11:22 PM
  2. Reminder settings of Office 2010 Outlook
    By Glenwood in forum Windows Software
    Replies: 1
    Last Post: 02-10-2011, 12:40 AM
  3. Can project send email reminder of task start date?
    By Dilbert in forum Microsoft Project
    Replies: 3
    Last Post: 01-06-2011, 10:55 PM
  4. Replies: 3
    Last Post: 10-11-2010, 07:27 PM
  5. Reminder for Due Date - MS Project 2007
    By BA Freyer in forum Windows Software
    Replies: 1
    Last Post: 29-10-2010, 03:54 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,266,952.95751 seconds with 17 queries