Hi
I think I’ve hit a brick wall with this one. I inherited a project plan that already contains some formula used to audit the project tasks on the plan. However there seems to be a problem with the formula that tracks the overdue activities on the plan, the formula is either not tracking accurately or the formula is wrong. pls see if you can interprete this:
Switch(Complete]<100) And ([Finish]<[Date1])),"Overdue",([Summary]=No),"No Error")
The above formula was applied to the example below but the task audit shows that the task is overdue even when the task start date is still in the future. In this case the project status date is 29/10/10. Date1 is the project status date.
Task audit -task name- duration -start- -finish- %comp
Overdue Train Trainers 1d Fri 22/10/10 Mon 25/10/10 0%