Hi there,
I've noticed the start date on my tasks which have a Finish to Start relationship with their predecessors, start on the same date the predecessor task ends.
eg.
Task Nm Duration Start Finish pred resource
task 1 1 day Mon 11/10/10 Tue 12/10/10 person 2
task 2 1 day Tue 12/10/10 Tue 12/10/10 1 person 2
task 3 4 days Wed 13/10/10 Mon 18/10/10 2 person 2
task 4 2 days Mon 18/10/10 Wed 20/10/10 3 person 2
what I want is for the sucessor task to start the day after the predecessor ends
e.g
Task Nm Duration Start Finish pred resource
task 1 1 day Mon 11/10/10 Mon 11/10/10 person 2
task 2 1 day Tue 12/10/10 Tue 12/10/10 1 person 2
task 3 4 days Wed 13/10/10 Mon 18/10/10 2 person 2
task 4 2 days Tue 19/10/10 Wed 20/10/10 3 person 2
Any idea's ?
Thanks