As a project/resource manager at my company I use a large Project system with a shared resource pool. These resources are all set up through Active Directory. The new Team Planner view is a fantastic addition and leads me to believe I can use Project for resource and time management. The only problem is that the Team Planner view does not offer great visibility in reports or print outs/pdfs as short tasks become illegibly small and any detail in the task title is lost.
What I am after is a way that I can export tasks to Outlook including any notes or files that are attached to them. I believe that in the past this would have been possible with the "set reminder" button but I can't get it to work at all. I have made the button visible in Project but it is simply greyed out no matter what I do.
I have also looked at various Project viewers that might allow me to distribute a "schedule" to resoureces but unfortunately I can't find any that incorporate the Team Planner view.
Any advice on this subject would be much appreciated. Thanks