Results 1 to 9 of 9

Thread: Adding Costs to Tasks

  1. #1
    Join Date
    Jul 2011
    Posts
    32

    Adding Costs to Tasks

    I have a project file containing fixed cost column. Due to some reason I need to add costs to different tasks but I am not able to get it done. I tried following some steps provided on few sites but it is not working for me. Can anyone here please let me know the perfect steps to do the same? Thank you.

  2. #2
    Join Date
    Sep 2004
    Posts
    133
    First of all, you will need to add a Cost field which will automatically capture both the Fixed and Variable Costs. Once done you will be able to move them up to summary level where you required it. I think this is the best way because if you type costs directly into the task Cost field, MSP will interpret this as Fixed Cost, which is any Cost that is associated with a task that does not come from resource costs.

  3. #3
    Join Date
    May 2010
    Posts
    6
    Today I noticed this same problem - in column Fixed Cost, the values don't add up. I understand the explanation, but can't we do some scripting here to fix this?

    Thanks for your good suggestion and explanation; it's all clear this way and I am happy with them.

    By the way - are there more oddities like this that one is likely to encounter in MSProject?

  4. #4
    Join Date
    Sep 2004
    Posts
    133

    Re: Adding Costs to Tasks

    I don’t think there might be any problem because Cost sums them all up as Fixed Costs are entered in the Fixed Cost field and Variable Costs are entered in the Resource Sheet automatically. Isn’t it?

  5. #5
    Join Date
    May 2010
    Posts
    6

    Re: Adding Costs to Tasks

    OK Thanx, I'll do that.

  6. #6
    Join Date
    Jan 2012
    Posts
    2

    Re: Adding Costs to Tasks

    I wonder if you could help me. I would like to do as recommedned: create a new custom field equal to fixed costs so that these are added up in the summary tasks, but I cannot see how to do this. Can you please help? Thank you!!

  7. #7
    Join Date
    Dec 2006
    Posts
    489

    Re: Adding Costs to Tasks

    Add one of the custom Cost fields (Cost1 for example) to the table.

    Once you have added the field, right click on the column heading to show the shortcut menu and select "Custom Field" or "Customize Field" if using Project 2007 or earlier.

    In the Custom Field dialog, select Formula under custom attributes.

    In the Formula dialog enter [Fixed Cost]. Click OK to return to the Custom Fields dialog.

    Under "Calculation for task and group summary rows", select "Roll up" and Sum.

    You may now enter your costs at the subtask level in the Fixed Cost field and the custom field will show the fixed cost entered and sum at the Summary Task level.

  8. #8
    Join Date
    Jan 2012
    Posts
    2

    Re: Adding Costs to Tasks

    It worked - how exciting! Thank you very very much!!!!

  9. #9
    Join Date
    Dec 2006
    Posts
    489

    Re: Adding Costs to Tasks

    You are very welcome and thanks for the feedback.

Similar Threads

  1. Task costs and annualised costs
    By m_albiges in forum Microsoft Project
    Replies: 3
    Last Post: 26-03-2013, 08:55 PM
  2. project with tasks and sub tasks
    By 54234121 in forum Windows Software
    Replies: 2
    Last Post: 29-04-2011, 11:47 AM
  3. Cityville: How much exactly does the expansion costs
    By Techie Boy in forum Video Games
    Replies: 3
    Last Post: 01-02-2011, 05:34 PM
  4. Windows Scheduled Tasks don't luanch if tasks not finished
    By Andy Candy in forum Windows Software
    Replies: 3
    Last Post: 21-08-2009, 11:47 AM
  5. Scheduled Tasks: Notify me of missed tasks
    By Hrishia in forum Windows XP Support
    Replies: 1
    Last Post: 02-01-2009, 02:45 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,728,470,879.49009 seconds with 17 queries