I am working on MS Project that I have been using from almost sometime now. I have set up a basic test schedule with 5 tasks, choosen task type duration and not selected effort driven. I also have 3 additional fields in the basic gantt view, which is, work, actual work and %complete. I have got a tasks of a fixed duration, that is, I have a 4 hour task that will take a 2 day duration. If I am populating the actual work field, then the %complete changes. But what if I have got a task with a dutration of 2 days, 5 hours per day, will the resource complete the task on day 2 in 3 hours? This seems that the planned hours were 10 hours, the actuals were 8 and the %complete is 100% leaving the 2 hours as an under-spend or time saved. Can anyone tell me a method to model this thing? Thanks