Can anyone tell me how Project calculates earliest and latest dates (times) for the following cases? I have checked the Task 1 (predecessor) and Task 2 (successor) linked with Finish-to-Finish or Start-to-Start dependency with lag or lead time. I have also found a couple of CPM guide on the internet but they only contain examples of Finish-to-Start dependency. What is the reason for this thing? Thanks.