I want to separate planned work and duration from actual. I have a task which is scheduled for start 4/7 Finish 4/8 work hours of 16, i want to adjust the entry table in a way so that it reflects actual start 4/7 and actual finish 4/9 along with hours. I have tried doing so but for some reason the actual work is coinciding with w/ duration at 3 days and actual work at 24 hrs. Is there anything that i might be missing, any help for this will be appreciated.