I have got some queries regarding tasks and predecessors. For an example, I am having the following tasks:
- Buy ingredients
- Bake cake
- Eat cake
- Cake project completed (milestone)
This tasks have each previous one as its predecessor. But for the last task, the milestone, each of the tasks 1-2 should be complete before it can be finished. So, should I make the predecessor tasks for task 4 as tasks 1,2,3? Or will it be fine to just put the task 3 as the predecessor for task 4, since task 3 will require task 2 that requires task 1, etc? Thanks.
Bookmarks