Results 1 to 4 of 4

Thread: Best practice - predecessor tasks

  1. #1
    Join Date
    Oct 2004
    Posts
    87

    Best practice - predecessor tasks

    I have got some queries regarding tasks and predecessors. For an example, I am having the following tasks:
    1. Buy ingredients
    2. Bake cake
    3. Eat cake
    4. Cake project completed (milestone)

    This tasks have each previous one as its predecessor. But for the last task, the milestone, each of the tasks 1-2 should be complete before it can be finished. So, should I make the predecessor tasks for task 4 as tasks 1,2,3? Or will it be fine to just put the task 3 as the predecessor for task 4, since task 3 will require task 2 that requires task 1, etc? Thanks.

  2. #2
    Join Date
    Nov 2005
    Posts
    1,323
    You need to first start by ensuring that every Task has atleast one FS Predecessor and one FS successor. That are the most proximate and obvious. That ensures a closed network with no open ends so that you can get a reliable result on the critical path. After that go through and look for the next most obviosu FS Predecessor for each Task. There are many tasks that will have more than one FS Predecessor, and you have to identify them all as predecessors, either directly or indirectly, or you might miss the CP.

  3. #3
    Join Date
    Jan 2010
    Posts
    1
    Can someone expand a little bit on the benefit of each task needing a predecessor and successor task? I understand the common sense benefits of using predecessors for a task that can't logically complete before another task finishes, but let's say 5 out of 10 project tasks can take place immediately. What's the benefit in Project of tying them to a "project start" Milestone? What are the risks of not doing so?

    Thanks.

  4. #4
    Join Date
    Mar 2010
    Posts
    1

    Re: Best practice - predecessor tasks

    Some clarification please. Going back to the original example, how would you recommend tying a new task, that does not have a successor, to the project “end” milestone? For example:

    1. Buy ingredients
    2. Bake cake
    3. Monitor oven temp.
    4. Eat cake
    5. Cake project completed (milestone)

    Thanks in advance for your reply.

Similar Threads

  1. Reschedule task if its predecessor ends early?
    By DavidD33 in forum Microsoft Project
    Replies: 11
    Last Post: 09-05-2012, 08:34 PM
  2. Will Prey 2 be as awesome as its predecessor
    By Vincent D in forum Video Games
    Replies: 6
    Last Post: 08-06-2011, 10:24 PM
  3. Windows Scheduled Tasks don't luanch if tasks not finished
    By Andy Candy in forum Windows Software
    Replies: 3
    Last Post: 21-08-2009, 11:47 AM
  4. Scheduled Tasks: Notify me of missed tasks
    By Hrishia in forum Windows XP Support
    Replies: 1
    Last Post: 02-01-2009, 02:45 PM
  5. Windows HPC Server 2008 and its predecessor
    By James Afflek in forum Guides & Tutorials
    Replies: 1
    Last Post: 12-12-2008, 03:28 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,715,840,899.31565 seconds with 17 queries