I am trying to update a lot of project files within the company and one aspect that needs updating is the Actual Finish Date. The Project has a planned Start Date and a Planned Finish date. These should remain as they are, but when I am trying to add the Actual Finish dare to the project, then it amends the Finish Column as well which I do not want it to do? Can anyone help me out? Thanks.