    Hey guys, I’m in need of some urgent help from you all regarding Resource Plans in Project 2007. I created a project plan after working for hours on the same but now when I click on View Assignments or View Availability, it says “I have no assignments and that I still have 40 hours available.” I don’t know why is it not working even after trying the same with two different contacts and 2 different projects. Any help would be appreciated!

  2. #2
    Join Date
    Sep 2004
    Posts
    75

    Re: Project Resource Plan

    Hello Sulolab, just try out the following steps. Hope you will get helped:
    • Start with removing the resources from the enterprise project, as the resources are not necessary.
    • Open the Resource Plan for editing.
    • Build your team in the Resource Plan to include the two resources whose time you want to reserve.
    • Expand the View Options pane at the top of the data grid.
    • Set the Date Range and Column Interval values as needed.
    • Set the Calculate Resource Utilization From value to Resource Plan.
    • Set the Work Units value to your desired booking method.
    • Click the Apply button.
    • In the data grid, enter the numbers for each resource for each time period.
    • Click the Save and Publish button.

  3. #3
    Join Date
    Oct 2010
    Posts
    1

    Re: Project Resource Plan

    Hi for your response above :
    4. Expand the View Options pane at the top of the data grid.
    5. Set the Date Range and Column Interval values as needed.

    Do I need some permissions to be able to set the inerval values? Because, I don't see a View Options pane. I have added resources to the plan and now want to set the column interval values. How do I do that? I am able to set the date range, but not able to figure out how to set the interval values. Please help!

    Thanks!

Similar Threads

  1. MS Project Resource Loading
    By 032664 in forum Microsoft Project
    Replies: 1
    Last Post: 26-01-2012, 11:26 PM
  2. Microsoft Project - Project - Trying to Show Resource Allocation
    By thisistony in forum Microsoft Project
    Replies: 2
    Last Post: 28-11-2011, 09:15 PM
  3. MS Project Resource Reporting
    By Mutso in forum Windows Software
    Replies: 2
    Last Post: 05-08-2011, 04:18 AM
  4. Project: resource use on tasks
    By proj03 in forum Windows Software
    Replies: 1
    Last Post: 28-01-2011, 11:12 AM
  5. MS Project - Resource Leveling
    By ra93013 in forum Windows Software
    Replies: 3
    Last Post: 21-01-2009, 06:30 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,714,036,774.18156 seconds with 17 queries