Results 1 to 2 of 2

Thread: ms project task resource setup

  1. #1
    Join Date
    Mar 2012
    Posts
    1

    question ms project task resource setup

    Hi All,
    I need to set up a project to schedule tasks on machines using resources.
    The machines (defined as a resource) are based on a 2-shift, 16hr calendar, 6am-10pm
    People resources are either am or pm shift, 6-2 or 2-10
    The project calendar is 16h, same as machines.
    I have experimented with all variations of fixed duration units, effort etc, but still get silly messages such as ' the resource is assigned outside ...'. at which point the duration is modified, or the usage is messed-up.
    I do not want to 'automatically' modify the duration.
    All I want to do is assign multiple resources to a task; e.g. assign one machine (as a resource) and 2 people (one per shift) to complete a 16 hr task. i.e. The machine resource would work for 16 hours, and each person 8 consecutively.
    Resources would work 100% of their time on one machine at a time.
    Is this possible in project? If so - please advise settings.
    thank you.

  2. #2
    Join Date
    Dec 2006
    Posts
    489

    Re: ms project task resource setup

    Have you also posted to the Microsoft Answers forums with this same question? See:

    http://answers.microsoft.com/en-us/o...1-4ba1b307f47c

    In the future, you might want to post your Project question at techarena to the forum specifically devoted to Project:

    http://forums.techarena.in/microsoft-project/

    You're more likely to catch someone with project background there than here.

Similar Threads

  1. Replies: 4
    Last Post: 20-04-2012, 11:22 PM
  2. Microsoft Project - Project - Trying to Show Resource Allocation
    By thisistony in forum Microsoft Project
    Replies: 2
    Last Post: 28-11-2011, 09:15 PM
  3. Ms Project 2007 Task setup
    By Mr Karlsson in forum Windows Software
    Replies: 1
    Last Post: 30-04-2011, 01:45 AM
  4. setup task in project 2007, need help!!
    By pc_s in forum Windows Software
    Replies: 2
    Last Post: 11-02-2011, 02:21 AM
  5. Project crash when assigning a resource to a task
    By BlackSunReyes in forum Microsoft Project
    Replies: 2
    Last Post: 06-04-2010, 02:49 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,557,725.20648 seconds with 17 queries