    MS Project Scheduling on specific day of week

    Hi There - is there a way to set-up a task in MS Project 2007 so that it always starts on the Monday following all predecessors being completed?

  2. #2
    Join Date
    Dec 2006
    Posts
    489

    Re: MS Project Scheduling on specific day of week

    Hi,

    Yes. It can be achieved with the use of a task calendar and a one-minute "buffer" task. Create a calendar where the only working time is one minute before the start time of your working day on every Monday. All other time should be non-working time.

    Add a one minute task as the predecessor to your Monday morning regular task. Assign the task calendar to the one minute predecessor. This will force the successor (your Monday task) to always start on the Monday following the completion of predecessor tasks.

    In the future, try posting to the forum for Project:

    see:
    http://forums.techarena.in/microsoft-project/

    I hope this helps.

    Julie

Similar Threads

  1. Replies: 2
    Last Post: 30-01-2012, 08:32 PM
  2. MS Project 2010 Resource Scheduling
    By shoppingboy in forum Microsoft Project
    Replies: 5
    Last Post: 29-11-2011, 10:07 PM
  3. MS project: change the week end in the calendar
    By Mohammed-aqel in forum Windows Software
    Replies: 1
    Last Post: 04-10-2011, 12:15 AM
  4. How is scheduling works in MS Project 2007
    By MILFORD in forum Windows Software
    Replies: 5
    Last Post: 24-12-2009, 05:49 AM
  5. Replies: 2
    Last Post: 02-05-2008, 08:54 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,911,483.85534 seconds with 17 queries