MS Project Scheduling on specific day of week

Hi There - is there a way to set-up a task in MS Project 2007 so that it always starts on the Monday following all predecessors being completed?
Reply With Quote
  #2  
Old 26-01-2012
Member
 
Join Date: Dec 2006
Posts: 489
Re: MS Project Scheduling on specific day of week

Hi,

Yes. It can be achieved with the use of a task calendar and a one-minute "buffer" task. Create a calendar where the only working time is one minute before the start time of your working day on every Monday. All other time should be non-working time.

Add a one minute task as the predecessor to your Monday morning regular task. Assign the task calendar to the one minute predecessor. This will force the successor (your Monday task) to always start on the Monday following the completion of predecessor tasks.

In the future, try posting to the forum for Project:

see:
http://forums.techarena.in/microsoft-project/

I hope this helps.

Julie
Reply With Quote
Reply

  TechArena Community > Software > Windows Software
Tags: , , , ,



Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "MS Project Scheduling on specific day of week"
Thread Thread Starter Forum Replies Last Post
MS Project help with duration and predessor scheduling HJM Windows Software 2 30-01-2012 08:32 PM
MS Project 2010 Resource Scheduling shoppingboy Microsoft Project 5 29-11-2011 10:07 PM
MS project: change the week end in the calendar Mohammed-aqel Windows Software 1 04-10-2011 12:15 AM
How is scheduling works in MS Project 2007 MILFORD Windows Software 5 24-12-2009 05:49 AM
How do I change the project calander from 5 day to 7 day week? Lynette Microsoft Project 2 02-05-2008 08:54 AM


All times are GMT +5.5. The time now is 04:58 AM.