Thread: MSProject how to make task complete out of hours

  1. #1
    Join Date
    Jan 2012
    Posts
    2

    MSProject how to make task complete out of hours

    I have a series of tasks that must be done out of hours and they must not be started unless they can be completed out of hours.
    For example 2 tasks that each take 2 hours, dependent on other tasks completing AND it being after 00:00 when they start and that they can complete before 00:59.
    I have set up a task calendar 00:01 - 05:59, but the tasks are getting scheduled if they can begin before 05:59, whereas I need them not to start unless they can complete beforw 05:059. These tasks will be done every weekday night for several weeks until the project is completed. Any ideas how I can do this?

    Thanks

  2. #2
    Join Date
    Mar 2011
    Posts
    212

    Re: MSProject how to make task complete out of hours

    Just see to this thread and see if this is helpful to you or not. They have discussed on the same and I hope it will be useful for you.

  3. #3
    Join Date
    Jan 2012
    Posts
    2

    Re: MSProject how to make task complete out of hours

    Thanks but that is just a general diiscussion about how to set durations, I have a specific need to make a task only start if it can end during the same outage window.

  4. #4
    Join Date
    Dec 2006
    Posts
    489

    Re: MSProject how to make task complete out of hours

    I would create a calendar with restricted working hours and use a buffer task. If the tasks take 1 hour and must be completed before 06:00 am then they can start no later than 4:59, yes?

    So create a more restrictive schedule than you have -- starting at 00:01 and ending at 04:59. Add a one minute duration predecessor to the task linked as the successor to the other predecessors. This will schedule the one-minute predecessor in the hours allowable to get the one hour task complete.

    In the future, you may also want to post directly to the forum for Project. See

    http://forums.techarena.in/microsoft-project/

    Julie

Similar Threads

  1. Replies: 3
    Last Post: 19-02-2012, 08:56 PM
  2. Replies: 1
    Last Post: 21-01-2012, 04:52 PM
  3. Replies: 6
    Last Post: 22-06-2011, 11:04 AM
  4. Replies: 6
    Last Post: 27-11-2010, 07:51 PM
  5. Capture Actual work when a task is complete
    By DWall in forum Microsoft Project
    Replies: 2
    Last Post: 18-07-2008, 06:38 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,495,320.49043 seconds with 16 queries