Hi All,
I am new to Microsoft Project 2010 and I am trying to understand how I can effectively schedule two or more resources against one task.
The scenario that I have is:
One task i.e. Requirements Gathering for two weeks
Two resource - Both work the same working times i.e. Mon - Fri, 9 - 5.30
Resource 1 is available Mon - Wed for week 1 and Mon - Fri for Week 2
Resource 2 is available Wed - Fri for week 1 and Wed - Fri for WeeK 2
How can I schedule my resources for this one task? I don't want to change their working weeks as the days in which they are available alters frequently and it may just be they are assigned to a different task on the same plan for the time they are not available for my requirements gathering task.
Is there anyway I can do this without creating multiple tasks?
Appreciate any help anyone can give!