I have a basic calendar question that is driving me nuts, need some help to understand the logic and make needed corrections for a custom calendar that will provide equal time frame for all time units. The Problem: I'm using the standard MS Project 2007 calendar. When I enter a duration for a task as "365 days" the duration is 6/1/11 to 10/23/12. When I enter a duration as "52 wks" the duration is 6/1/11 to 5/29/12. When I enter a duration as "12 mons" the duration is 6/1/11 to 5/1/12. How can this be? Why is the duration not exactly the same for each entry type?