Thread: Brewery Task Lengths for Project 2007

  1. #1
    Join Date
    Feb 2010
    Posts
    1

    Brewery Task Lengths for Project 2007

    I am evaluating Project 2007 for scheduling tasks in my Brewery.

    My resources are tanks (FERM 1, FERM 2, etc).

    My tasks are stages in the brewing process. I want tasks to be scheduled in increments of whole days, starting at the very beginning of a day and ending at the very end of they day.

    Here is a simplified task list:

    Task: Beer batch #1

    Subtasks:

    1. Brew 1 day, resource: FERM 1
    2. Fermentation 8 days, precursor: 1, resource: FERM 1
    3. Condition 3 days, precursor: 2, resource: FERM 1
    4. Rack 1 day, precursor: 3, resource: FERM 1, FERM 2
    5. Condition 7 days, precursor: 4, resource: FERM 2
    6. Carb 1 day, precursor: 5, resource: FERM 2
    7. Bottle 1 day, precursor: 6, resource: FERM 2


    This lets me schedule based on tank occupancy.

    I set up a 24 hr calendar with 24 hr/day, 7 days/wk, and 28 days/month. This is my project calendar and my resource calendar.

    I also have another calendar that is similar, but has no weekend work days.

    Project seems to refuse to schedule my tasks from 12am to 12 am., which messes up my calendar view. How can I force every task to fall within the bounds of a single day?

    Thoughts?

  2. #2
    Join Date
    Mar 2010
    Posts
    183

    Re: Brewery Task Lengths for Project 2007

    You might need to work more on that. Enter the list of tasks and activities prior to each task. It also identifies groups of tasks, we divide the project into phases to calculate the timing of different phases. Later we enter the resources and we can calculate the cost of the project. I will recommend you to go for some kind of tutorial for this. There are very less information available for Microsoft Project.

Similar Threads

  1. Replies: 4
    Last Post: 20-04-2012, 11:22 PM
  2. Ms Project 2007 Task setup
    By Mr Karlsson in forum Windows Software
    Replies: 1
    Last Post: 30-04-2011, 01:45 AM
  3. Project 2007 summary task duration help please?
    By KNLee in forum Windows Software
    Replies: 3
    Last Post: 24-04-2011, 02:03 AM
  4. setup task in project 2007, need help!!
    By pc_s in forum Windows Software
    Replies: 2
    Last Post: 11-02-2011, 02:21 AM
  5. Project Professional 2007 task duration
    By iShree in forum Microsoft Project
    Replies: 3
    Last Post: 04-08-2009, 06:24 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,714,111,410.45788 seconds with 16 queries