    I'd like to subtract today's date from a task finish date to determine the number of days left to complete that task at a glance. I can do this but the result is some cryptic number instead of just whole days. Any suggestions?

  2. #2
    Join Date
    May 2008
    Posts
    979

    Re: Subtracting dates in Project 2007

    Create a new custom number field and subtract the finish date from the current date using ProjDateDiff() or DateDiff(). You can also refer to the Help button placed on the pages under Menu: Tools/Customize/Fields. It will guide you in a much better way.

Similar Threads

  1. MS-Project > Linked tasks, but dates dont' move
    By BefuddledSearcher in forum Windows Software
    Replies: 2
    Last Post: 30-01-2012, 08:27 PM
  2. importing dates from ms excel into ms project
    By tazor in forum Microsoft Project
    Replies: 2
    Last Post: 14-12-2011, 10:20 PM
  3. MS Project 2003 - show dates in the header of the report
    By shoppingboy in forum Windows Software
    Replies: 2
    Last Post: 28-03-2011, 01:08 PM
  4. Project 2003 - Print Gantt Chart BetweenTwo Dates
    By CeeTee in forum Microsoft Project
    Replies: 2
    Last Post: 29-04-2009, 07:53 PM
  5. Understanding Project tasks and dates
    By Javan in forum Windows Software
    Replies: 2
    Last Post: 05-09-2008, 11:32 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,515,489.37515 seconds with 17 queries