MS Project 2007 Current date column

Im using MS Project 2007 Proffessional and want to add a column that shows the current date. Does anyone know how I can do this ?
Reply With Quote
  #2  
Old 19-05-2010
Member
 
Join Date: Dec 2007
Posts: 1,728
Re: MS Project 2007 Current date column

Follow the below method to:

1. On the Tools menu, click Options, and then click the View tab.
2. In the Date format box, click the date format that you want to use.
  • You can change the date format for a specific table (table: A set of columns that shows specific information about tasks, resources, and assignments in a sheet view.). On the View menu, point to Table, and then click More Tables. In the Tables list, click Task or Resource, click the table for which you want to format the date, and then click Edit. In the Date format box, click the date format you want to use. Click OK, and then click Apply.
  • If you don't see the date format you want, use the Control Panel to change the date settings as needed.
Reply With Quote
  #3  
Old 20-05-2010
Member
 
Join Date: Jul 2009
Posts: 67
Re: MS Project 2007 Current date column

Thanks for your thoughts James 911. Perhaps I'm doing something wrong but your solution isnt producing what I had hoped. I'd like a column that automatically shows the current date (the date in the column should change on a daily basis).
Reply With Quote
  #4  
Old 21-05-2010
Member
 
Join Date: Oct 2004
Posts: 1,342
Re: MS Project 2007 Current date column

You can also try to do the following option: Tools / Options / Schedule / New tasks : Start on Current Date You could also insert the Created field : Insert / Column / Created. This will set the date Column to Automatically change to todays date. Hope this helps
Reply With Quote
Reply

  TechArena Community > Software > Windows Software
Tags: , , ,



Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "MS Project 2007 Current date column"
Thread Thread Starter Forum Replies Last Post
Need help to access Current Date filter on Microsoft Project lopa Microsoft Project 12 30-03-2012 08:21 PM
MS Project 2007 Task Usage - Baseline Cost / Work vs. Current Cost / Work Planning_Nate Microsoft Project 3 29-06-2011 09:31 PM
Baseline Column Date automatically updates Finish Date Adam 1980 Microsoft Project 3 18-05-2011 06:08 PM
Reminder for Due Date - MS Project 2007 BA Freyer Windows Software 1 29-10-2010 03:54 AM
Project 2007: Actual Finish Date & Finish Tahseen Shahzad Microsoft Project 3 08-10-2008 04:53 PM


All times are GMT +5.5. The time now is 03:09 AM.