How to remove/ignore the 'time' from the start/finish columns

I have created a column with red and green indicators that display following this formula - [Finish]<=[Baseline Finish]
Yes = green
No = red

So if the Finish date has slipped and occurs after Baseline Finish, the column will show a Red circle against that task, otherwise it is green.

It works ok apart from the instance when the only difference in the finishing dates are the actual times of completion, on the same day. Sometimes Project will be showing a task finishing at 12pm and the baseline finishes at 5pm, so it will mark that task as RED.

But this programme is not being micromanaged to the level of hours, just days, so I would like to know how to write a formula that is based on - [Finish]<=[Baseline Finish] - but ignores the time differences, OR a way of not including the 'time' in the start/finish fields.

Can this be done?? Many thanks if you can provide a solution!!
Reply With Quote
  #2  
Old 12-02-2010
Bull50's Avatar
Member
 
Join Date: Nov 2008
Posts: 1,262
Re: How to remove/ignore the 'time' from the start/finish columns

Reformat the formula of Finish like this one -

Quote:
Format(Finish,"ddd mm/dd/yy ")
and Baseline Finish as
Quote:
Format(Baseline Finish,"ddd mm/dd/yy ")
Reply With Quote
Reply

  TechArena Community > Software > Windows Software


Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads for: "How to remove/ignore the 'time' from the start/finish columns"
Thread Thread Starter Forum Replies Last Post
Can I establish start and finish time for specific task? Damon Microsoft Project 6 04-02-2011 01:15 AM
Start to Finish relationship Shreepad Gandhi Microsoft Project 3 28-05-2010 06:30 AM
Remove Time from Start/Finish Date Columns When Exporting to Excel Colleen Microsoft Project 2 15-04-2010 03:57 AM
Start and Finish defaults A. Butch Microsoft Project 3 10-10-2009 04:48 AM
Lag time between Start-Date and Finish-Date Shahriar N k Microsoft Project 5 22-01-2009 09:42 PM


All times are GMT +5.5. The time now is 01:50 AM.