I don't even know what to ask....so here goes....
In MS Project 2007, I create a number of tasks and assign Work in hours for that task. The intent is to create a list of tasks for that week, with the total work hours for those tasks equal to forty hours.
However, Resource usage and Task usage then show over allocations, as project evidently assigns 8 hours to each task each day until the Work hours I entered for that task are used up, instead of equally distributing the work hours for that task across the week.
So when I enter:
Task Work
Task 1 8 h
Task 2 16 h
Task 3 16 h
Project gives me:
M T w Th F
Task 1 Work 8
Task 2 Work 8 8
Task 3 Work 8 8
Looking like I want 24 hours of work on Monday, 16 hours on Tuesday, and none on W, Th, F.
How do I fix this?