Thread: SPI Issue

  1. #1
    Join Date
    Jul 2009
    Location
    California
    Posts
    1

    Arrow Project SPI issue

    My team and I are trying to figure out why Project is calculating something a certain way. See picture attached.
    We are not sure why the highlighted line would equal 27% when one of the jobs is complete? Shouldn't this be much higher?


    I left the Requirements Development section in that picture because that shows it is calculating correctly (all but one job is finished = 99%)

  2. #2
    Join Date
    Jan 2009
    Posts
    710

    Re: SPI Issue

    See the last section on the picture which says "Mechanical/Electrical ICD (from..." that task is show as 0% may be that is affecting the total calculation...

Similar Threads

  1. Replies: 6
    Last Post: 12-06-2011, 01:02 AM
  2. DP35DP: memory issue; DVD issue; Lan issue.
    By Rivan in forum Motherboard Processor & RAM
    Replies: 5
    Last Post: 29-06-2010, 12:50 AM
  3. Replies: 4
    Last Post: 03-04-2010, 06:03 AM
  4. DNS issue causing "Applying computer setting issue" hang
    By NIcaBoy in forum Small Business Server
    Replies: 2
    Last Post: 14-10-2009, 06:04 PM
  5. Vpn Issue
    By quinn24 in forum Networking & Security
    Replies: 3
    Last Post: 25-10-2008, 08:26 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,714,159,112.42126 seconds with 16 queries