Thread: Need help w/ MPP 2007 EPM - dates revert back

  1. #1
    Join Date
    Jun 2009
    Posts
    3

    Need help w/ MPP 2007 EPM - dates revert back

    Hello,

    I am having a problem w/ dates reverting back in my schedule on MPP EPM 2007.....when I publish the schedule to EPM I find that some dates are reverting back to the original unchanged date. As a workaround...we have found that zeroing out the status for each resource, making the new date change, saving, and then re-entering the status for each resource and re-saving fixes the problem....

    Recently, we are implementing the same workaround and getting dates reverting back again. Has anyone experienced this, and found a root cause and potential solutions?

    Thanks! Great board and resource!
    Last edited by ryan1010; 24-06-2009 at 10:17 PM.

  2. #2
    Join Date
    Dec 2007
    Posts
    1,547

    Re: Need help w/ MPP 2007 EPM - dates revert back

    Do you have SP-1 installed to Project 2007? What operating system are you using? Are you working with Project Server? Take a look at this similar type of topic discussion made below

    Changing start date and creating formula for finish date

  3. #3
    Join Date
    Jun 2009
    Posts
    3

    Re: Need help w/ MPP 2007 EPM - dates revert back

    Quote Originally Posted by team leader View Post
    Do you have SP-1 installed to Project 2007? What operating system are you using? Are you working with Project Server? Take a look at this similar type of topic discussion made below

    Changing start date and creating formula for finish date
    Thanks...yes SP-1 is installed. Windows XP.

    Yes...I use Project Server. Microsoft Project Pro (MPP) in EPM (Enterprise Project Management)...will review link. Thanks much!

  4. #4
    Join Date
    Jun 2009
    Posts
    3

    Re: Need help w/ MPP 2007 EPM - dates revert back

    Thanks for the link.

    I checked it out, but do not believe it to apply to my situation.

    Basically, and perhaps it's a glitch w/ our system (tailored for our use), we:

    1) Have a task w/ resources loaded under it.
    2) Accept % Complete updates through PWA, and publish the schedule to reflect in EPM.
    3) A date change request from a PM will come in.
    4) If I don't zero out the already accepted statuses on each individual resource and then change the date to the new date the PM wants, save, and then re-enter the status for each resource....the date will revert back to it's previous date.
    5) Hope this is articulated decently...if not my apologies. Not trying to waste anyone's time here.
    6) The above is a work-around to accomodate requests we get from PMs.
    Recently we are seeing our dates revert back even after we follow the work-around which has been successful.
    7) Is there any other reason a date would revert back from a resource(s) on it's own.

    Thanks again for your time.

Similar Threads

  1. How to revert back to IE 10 from IE 11
    By Bryant in forum Technology & Internet
    Replies: 3
    Last Post: 16-08-2013, 06:15 PM
  2. Replies: 5
    Last Post: 04-02-2012, 06:30 AM
  3. How to revert back to older version from Mozilla Firefox 4?
    By Jugo in forum Technology & Internet
    Replies: 4
    Last Post: 29-03-2011, 10:23 AM
  4. N900 unable to revert back to Maemo.
    By BaBHUshA in forum Portable Devices
    Replies: 4
    Last Post: 25-01-2011, 10:31 AM
  5. How to revert back to 2003 after uninstalling 2007
    By Genesee in forum Office Setup
    Replies: 3
    Last Post: 18-02-2007, 02:29 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,419,206.22821 seconds with 17 queries