Hello,
I am having a problem w/ dates reverting back in my schedule on MPP EPM 2007.....when I publish the schedule to EPM I find that some dates are reverting back to the original unchanged date. As a workaround...we have found that zeroing out the status for each resource, making the new date change, saving, and then re-entering the status for each resource and re-saving fixes the problem....
Recently, we are implementing the same workaround and getting dates reverting back again. Has anyone experienced this, and found a root cause and potential solutions?
Thanks! Great board and resource!