    ms project --Gantt chart based on Actual %

    hiii alll, plss help

    We had to convert a pdf file into MS Project. We have typed out everything in MS Project. The following are the points we need clarification on:

    1. There are entries for Early Start, Early finish, Planned start and Planned finish (dates) and Planned and actual percentage. (We are getting Gantt charts based on planned %, but we require the Gantt chart bar to be based on Actual %)

    2. There are tasks which we have starting & ending on same date. The Gantt chart bar we get is for early start/ early finish, but what we require is Planned start/ planned finish.

    3. We know what are the critical items from the pdf file. But how do we mark so in the MS Project file?


    Have attached one page of the pdf file so that you can get a better idea. Please reply even if u can clear only one point....

    Thanks,


    sithara

  2. #2
    Join Date
    Dec 2007
    Posts
    1,599

    Re: ms project --Gantt chart based on Actual %

    Project Requests do not appear in a timeline gantt.

    Projects themselves will and in PPM6 it will be in the Executive tab. Select the view you want from the "More Views" list - or create one which meets your parameters and then switch format to Timeline Gantt. I suggest placing projects under a portfolio then creating a view that groups by parent project. This will give you what you are looking for.

    also, the Timeline Gantt is based off of the Planned Start and Planned finish date in the Project Profile if there are no tasks in the project. If there are Tasks then the Timeline Gantt is based off of the earliest Task start, last Task finish.

    A feature enhancement will be to show the Project Requests in the Executive tab Timeline Gantt.

  3. #3
    Join Date
    May 2009
    Posts
    5

    Re: ms project --Gantt chart based on Actual %

    thanks for ur reply ,,,but i want to get the solution in detail......
    im new to ms project

  4. #4
    Join Date
    May 2008
    Posts
    4,831

    Re: ms project --Gantt chart based on Actual %

    I think you should used a WBS Chart Pro which is a Windows-based project management software application that is used to create and display projects using a Work Breakdown Structure (WBS) Chart. A WBS chart displays the structure of a project showing how a project is organized into summary (phase) and detail levels. Using a WBS chart is a more intuitive approach to planning and displaying a project.

  5. #5
    Join Date
    May 2009
    Posts
    5

    Re: ms project --Gantt chart based on Actual %

    ohh!....plsss help.....

  6. #6
    Join Date
    Jan 2009
    Posts
    12

    Re: ms project --Gantt chart based on Actual %

    Try this
    http://www.download3k.com/Business-F...ment-Free.html
    I hope this is what you need.
    Don't have any idea with Ms Project.

  7. #7
    Join Date
    May 2009
    Posts
    5

    Re: ms project --Gantt chart based on Actual %

    noo ...

  8. #8
    Join Date
    Mar 2008
    Posts
    258

    Re: ms project --Gantt chart based on Actual %

    Iqbal, as per my knowledge PDF to MS project direct conversion ie.PDF=>MS Project, is not possible you need to go through anyone of middleware application, such as you need to check for the MS Project=>convertible application=>PDF or vice-versa, then only this is possible. so then please check for anyone of convertible application as per your requirement. Hope you understand your requirement.

  9. #9
    Join Date
    May 2009
    Posts
    5

    Re: ms project --Gantt chart based on Actual %

    yes i understood.
    but pdf to be converted into which middleware application?
    what software to be used to convert that middle ware to ms project

  10. #10
    Join Date
    Jan 2010
    Posts
    5

    Re: ms project --Gantt chart based on Actual %

    With a Microsoft Project 2007 Gantt chart, you can illustrate a project schedule by using graphical elements to represent tasks and the dependencies between them, and track how changes in one task affect the others.

    Microsoft Office Gantt Chart

    Also search in microsoft website for pdf they have an option or addins for PDF. u can even search from the given link as well.

  11. #11
    emily01 Guest

    Re: ms project --Gantt chart based on Actual %

    I would go with Valerie..

    Microsoft Office Project 2007 Gantt Chart - Illustrate a project schedule by using graphical elements to represent tasks and the dependencies between them.
    Microsoft gantt

    And you can find the pdf to Microsoft project converter

Similar Threads

  1. Print out of GANTT Chart Project 2010
    By KOVID in forum Microsoft Project
    Replies: 1
    Last Post: 26-03-2010, 03:43 PM
  2. Add a Text Note to a Gantt chart in project
    By rasena in forum Microsoft Project
    Replies: 4
    Last Post: 25-01-2010, 04:13 PM
  3. export gantt chart from Project 2007 to Excel
    By hatred in forum Microsoft Project
    Replies: 6
    Last Post: 16-11-2009, 09:37 PM
  4. Project 2003 - Print Gantt Chart BetweenTwo Dates
    By CeeTee in forum Microsoft Project
    Replies: 2
    Last Post: 29-04-2009, 07:53 PM
  5. Replies: 1
    Last Post: 05-04-2005, 08:11 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,711,698,137.97189 seconds with 17 queries