hiii alll, plss help
We had to convert a pdf file into MS Project. We have typed out everything in MS Project. The following are the points we need clarification on:
1. There are entries for Early Start, Early finish, Planned start and Planned finish (dates) and Planned and actual percentage. (We are getting Gantt charts based on planned %, but we require the Gantt chart bar to be based on Actual %)
2. There are tasks which we have starting & ending on same date. The Gantt chart bar we get is for early start/ early finish, but what we require is Planned start/ planned finish.
3. We know what are the critical items from the pdf file. But how do we mark so in the MS Project file?
Have attached one page of the pdf file so that you can get a better idea. Please reply even if u can clear only one point....
Thanks,
sithara