Thread: project milestone

  1. #1
    Join Date
    Apr 2009
    Posts
    1

    project milestone

    Does anyone know how to set a milestone to automatically move to the current date if the linked task has not started?

  2. #2
    Join Date
    Apr 2008
    Posts
    2,139

    Re: project milestone

    A milestone is a reference point that marks a major event in a project and is used to monitor the project's progress. Any task with zero duration is automatically displayed as a milestone. You can also mark any other task of any duration as a milestone.

    You can create milestones in your project to represent external tasks (external task: A task that represents a linked task in another project, providing an easy way to review the attributes of linked tasks without switching between projects. An external task can be changed only in the source project.). For example, one of your project's tasks requires an application being developed by another company. You can create a milestone with zero duration in your project to represent the completion of that application.

    Create a milestone with zero duration

    1. On the View menu, click Gantt Chart.
    2. Type the name of the new milestone in the Task Name field for the first empty row in the list.
    • If you are turning an existing task into a milestone, skip this step.

    3. Type 0 in the Duration field of the milestone, and then press ENTER.
    • When you type a duration of zero for a task, Office Project Professional 2007 automatically displays the milestone symbol Icon image in the Gantt Chart view on that day.

  3. #3
    Join Date
    Oct 2008
    Posts
    336

    Re: project milestone

    Here is help for you : http://annaforss.spaces.live.com/blo...C5B7!305.entry , Good luck

  4. #4
    Join Date
    Feb 2008
    Posts
    129

    Re: project milestone

    hi,

    You may also get very good Tutorial here as well,http://www.pragsoft.com/poms/help/Chapter4.html


    Hope this helps!!
    Regards,

Similar Threads

  1. Replies: 4
    Last Post: 20-04-2012, 11:22 PM
  2. Replies: 1
    Last Post: 20-08-2010, 01:27 AM
  3. Milestone won't turn on
    By Kanakpriya in forum Portable Devices
    Replies: 5
    Last Post: 22-04-2010, 06:43 AM
  4. Milestone USB troubles
    By Langward in forum Portable Devices
    Replies: 5
    Last Post: 22-04-2010, 05:46 AM
  5. Milestone View on Microsoft Project
    By Jimmy G in forum Microsoft Project
    Replies: 2
    Last Post: 01-02-2008, 08:42 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,713,534,315.85536 seconds with 17 queries