Ok, I made a dumb mistake. I have a master project that has a number of sub-projects. All of the sub-projects use a common resource pool.
I wanted to change the name of a sub-project, which I did using Windows Explorer.
Now the master project and the resource pool show the resources for the project I renamed as being over-allocated by 100% (200% total allocation)
How can I fix this.