Hi, Is there a simple way to find the total work planned to be done at a certain date for the project?
Thanks!
Andy
Hi, Is there a simple way to find the total work planned to be done at a certain date for the project?
Thanks!
Andy
hi
can you provide some more information like project is regarding which platform ??
hi
check this link.hoping it will help you .
http://www.dovico.com/help/dovtime9/...ft_project.htm
Hi, not quite.
I have a number of projects and I need to know how many of the days we should have worked, have we actually done.
For example I would like to be able to look my project and see how many work days should have been completed at the current date.
i.e in a project of 100 days, how many of these should have been done by today.
Is this possible?
I'm using Project 2007.
Thanks,
Andy