In standard MSP professional 2003 can you get the project name to come over with the activity name to a resource pool? It is tricky identifying tasks from a sub plan when you have 1 person allocated to several projects.

As far as I can see only the task information comes across with resource details thus meaning you need to put a project identifier on all tasks if you want clarity which is burdensome.

Help appreciated!