    question Task duration - start set by SF, finish set by FF. Can it be done & how ?

    Hi all.

    I would like to create a task in project 2003 with the following start and finish criteria
    start date set by the finish date of an earlier task
    finish date set by the finish date of a later task

    This task will have 1 resource assigned to it.

    I want to be able set the work independently of the duration of this task.

    Can this be done ?

    Reg.

  2. #2
    Join Date
    May 2008
    Posts
    3,971
    Well I don't think that this task can be set using Project 2003. However can you explain me what you want to set in this task and are you talking about Gantt Chart for setting the task?

  3. #3
    Join Date
    Sep 2008
    Posts
    2

    Hi SwitchBlade, thanks for your reply.

    You're right, I'm working in the Gantt Chart.

    We run lots of small projects. (3-6months from begining to end)

    There are a few project start up tasks that run before the customer provides us with as order. Once we accept the order, there is an "Oversight" task we run from the end of the "order acceptance task" until the end of "customer acceptance". After this there are a number of tasks we run to close the project.

    So I would like to have the "Oversight" task start when the "Order Acceptance" task finishes and finish when the "Customer Acceptance" task finishes.

    Is that possible or do we have to resort to VBScript or such like ?

    Reg.

  4. #4
    Join Date
    Aug 2009
    Posts
    4

    Re: Task duration - start set by SF, finish set by FF. Can it be done & how ?

    I also have a question...
    Suppose A and B is working on the same project. On a particular date say for example 12/Aug/2009, A starts working on a task 'x' and B starts working on task 'y'. 'x' will take only 1.1 day but 'y' will take 2.2 days. After completing the task 'y' A has to join with B for doing task 'y'. So my problem is, when i am allocating some % (say for example 25 %) of "A"'s work for task 'y' , office project is showing over allocation on 12/Aug/2009. How will i rectify it. Please help me.

Similar Threads

  1. Incorrect end date for a task with the same duration
    By vsaddepalli in forum Microsoft Project
    Replies: 2
    Last Post: 14-12-2011, 10:15 PM
  2. Replies: 1
    Last Post: 23-04-2011, 07:00 PM
  3. Can I establish start and finish time for specific task?
    By Soumen in forum Microsoft Project
    Replies: 5
    Last Post: 04-02-2011, 01:15 AM
  4. Task Start & Finish dates
    By Antonio00 in forum Microsoft Project
    Replies: 6
    Last Post: 17-03-2009, 09:48 PM
  5. Summary Task Duration incorrect
    By Hardik in forum Microsoft Project
    Replies: 3
    Last Post: 10-10-2008, 07:37 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Page generated in 1,714,002,332.71241 seconds with 17 queries