This will be achieved by PV and EV is calculated only from the lowest activity and accumulated on the upper levels. The difficulties of the baseline rollups for ex post transactions in the collection process and the project summary task are resolved. You only need the basic plan for the new selective operations to store, and already they are included in the EVA correctly. The fields I call EV method with a table that defines the acceptable methods for the Planned Value PV and EV for the Earned Value.
Code:
Cost field PV
Switch ([EV-method] = "none"; 0;
[EV-method] = "as scheduled", [BCWS];
[Projected Top]>] [status date; 0;
[Planned end] <= [state date];] [Planned costs;
[EV-method] = "0 / 100", 0;
[EV-method] = "20/80", 0.2 *] [Planned costs;
[EV-method] = "50/50", 0.5 *] [Planned costs;
True, 0)
Code:
Cost field EV
Switch ([EV-method] = "none"; 0;
[Actual Finish] = [] end;] [Planned costs;
[Actual Start] <]> [start, 0;
[EV-method] = "as scheduled", [BCWP];
[EV-method] = "0 / 100", 0;
[EV-method] = "20/80", 0.2 *] [Planned costs;
[EV-method] = "50/50", 0.5 *] [Planned costs;
True, 0)
The switch function has as arguments a list of value pairs, each consisting of a logical expression and the associated probability value. The list is processed from left to right. Once a logical expression "true" result, the cell value and the processing is terminated. Therefore, as the last pair of values "True, 0" is inserted so that the field always has a defined value.
Bookmarks