Problem 2

Another project requires completion of activities A, B, C, D, E, F, G, H, I, J, and K. The activity durations and precedence relationships are given below:



Activity Duration (Days) Predecessor



A 5 -

B 8 -

C 5 A

D 8 B, C

E 5 A, D

F 10 D

G 12 F

H 8 E, F

I 5 G, H

J 7 H

K 4 I, J



Use Microsoft Office Project or FREEPROJ software to solve the problem. Use activity names to be the letter followed by a dash and your initials (i.e., activity ‘A’ will be named ‘A-JS’ for the student Joe Smith.) Please add columns showing Earliest Start Time, Latest Finish Time, Total Slack, Critical Activities, and Free Slack assuming that the project needs to be completed as soon as possible. Please print the Table, Gantt chart, and the Network Diagram and submit it along with the solution to problem 1.