Many thanks for reply. I thought my thread might be confusing. I totally understand the processes of creating a Baseline and have not confused the "Start" and "Finish" fields as the baseline.
...
Type: Posts; User: Adam 1980
Many thanks for reply. I thought my thread might be confusing. I totally understand the processes of creating a Baseline and have not confused the "Start" and "Finish" fields as the baseline.
...
Hello
I looking for a solution, whether within MS Project functions or the use of a macro to automatically update the finish column date, if the Baseline date for that column is changed to a date...
Hello,
I'm currently using a formula allowing me to show trafiic lights (RAG). My formual also works well for the subtasks, but the highest level summary tasks shows the RAG status for the overall...
Hello,
I'm currently using a formula allowing me to show trafiic lights (RAG). My formual also works well for the subtasks, but the highest level summary tasks shows the RAG status for the overall...
Hello,
I have a similar problem as Manique 01. I'm currently using a formula allowing me to show trafiic lights (RAG). My formual also works well for the subtasks, but the highest level summary...