Search:

Type: Posts; User: niravrph

Search: Search took 0.02 seconds.

  1. Replies
    2
    Views
    2,049

    Decimals in Duration field

    Hi All,

    Had to change the Start & Finish fields to "Actual Start" & "Actual Finish". However since I've done that, the Duration field now shows decimals e.g. 2.13 days.

    How can I resolve this...
  2. Replies
    5
    Views
    2,095

    Re: Add Legend to Table

    Julie,
    Worked perfectly. Thanks - as always.
    NIRAV
  3. Replies
    5
    Views
    2,095

    Re: Add Legend to Table

    Hi James, all,

    I think you may be misunderstanding. What I am looking for help on is how I can match the ROWS on the Table (printed on one page) and the Chart (printed on another page). Right now...
  4. Replies
    5
    Views
    2,095

    Add Legend to Table

    Hi,

    MS Project automatically adds a Legend to the Chart view. Trouble is, due to overall length, I need to print out the Table & Chart separately (two separate *.pdf's) and because of the legend...
  5. Replies
    4
    Views
    2,077

    Re: Import from Excel - dates changed

    Julie,

    Great idea!

    Thanks,
    Nirav
  6. Replies
    4
    Views
    2,077

    Re: Import from Excel - dates changed

    Hi Julie,

    Okay. I got what you're saying. As is sometimes the case it was a matter of a new employee (me) given multiple Excel tracking sheets and being asked to migrate the data into a...
  7. Replies
    4
    Views
    2,077

    Import from Excel - dates changed

    Hi,

    I'm sorry but I will have to ask another basic question. I was given an Excel spreadsheet with two columns: Start Date and Finish Date. Since the entries were over 100 rows long I thought to...
  8. Replies
    19
    Views
    3,771

    Re: Remove unnecessary months/Quarters

    Julie,

    That did it! I had (the default was, apparently) 10 columns in the View tab. I reduced it to 4 and the view is now what I need. I had previously reduced the column widths on the left to...
  9. Replies
    19
    Views
    3,771

    Re: Remove unnecessary months/Quarters

    Julie,

    I have Scaling set to 70% of normal size right now. If I try and change it to 100% and do Print Preview I get an error message saying:

    1. "Reduce the width of the columns" (would love to...
  10. Replies
    19
    Views
    3,771

    Re: Remove unnecessary months/Quarters

    Julie,
    Okay I used that - but the printout still shows 2012, 2013. The issue is that I don't have ANY activity in 2012 etc. but the printout keeps printing these columns which eats up valuable real...
  11. Replies
    19
    Views
    3,771

    Re: Remove unnecessary months/Quarters

    Hi Julie,

    I am using MS Project 2007. I actually inputted 15-Mar. to 15-Jul. to try and zero in on just those times of maximum activity but I am still getting a "too expansive" printout, see...
  12. Replies
    19
    Views
    3,771

    Re: Remove unnecessary months/Quarters

    One more thing: I inputted 2011 as the range to Print, but I still get the printout looking like the attached. See attached.

    Thank you again for your help.
    Nirav
  13. Replies
    19
    Views
    3,771

    Remove unnecessary months/Quarters

    Hello,

    My Gantt chart view scrolls to the right showing 1Q2012, 2Q2012, 2Q2012 etc. My project doesn't last that long and these blank columns/rows show up on my print view. The key dates that my...
Results 1 to 13 of 13